I Electric Bill a dik leh dik loh chhut ve rawh le
Consumer te i harh ang u XXVIII
- Laldinpuia, Secy Serchhip District Consumer Assn.
Kawlphetha hi kan nunphungah hian a pawimawh ta em em mai a. A tel lovin kan awm hlei thei tawh lo. Kawlphetha kan hman man Electric bill te hi tunah chuan a chhut a awlsam tawh a, meter reader ten reading an lak chu computer hmanga chhut chhuah vek a ni tawh a, amaherawhchu computer operate tu chu mihring tho an nih avangin tihsual palh te pawh a awm thin a, hetianga Bill tihsual a awm chang chuan Department a complaint hi mipui ten kan tihtur leh kan chanvo a ni, kan bill diklo kha pek hmain kan complaint ngei ngei tur a ni(Bill pek phawt hnua complaint hi tih loh tur a ni).
Electric bill hi tariff mumal tak hmanga chhut vek a ni a, chu an chhut na tariff chu kan hriat chuan mipui ten kan Electric Bill a dik leh dik loh te hi kan hre thei a, kan bill chawi tur zah dik tak kha kan chhut ve thei vek a ni. April 2021 atangin Mizoram pumah Tariff Order thar kan hmang a. A hma ai chuan tlemin kan eng chhit man a to ta hret. Mipui nawlpui (Domestic Connection nei) tena kan bill chhut dan awlsam tak lo tarlang dawn ila –
Unit Consume |
Energy charges |
Fixed charge |
Meter Rent |
0 – 100 kWh |
Rs 4.80 / kWh |
Rs 50 per contracted load in kW |
Rs 20 for Single phase and Rs 35 for third phase. (Meter mahni a lei tan meter rent chawi a ngailo) |
101 – 200 kWh |
Rs 5.50 / kWh |
Rs 50 per contracted load in kW |
|
200 and above |
Rs 5.90 / kWh |
Rs 50 per contracted load in kW |
Khi khi tuna kan tariff hman lai mek a ni a. I Electric Bill-a a dinglam laihawl vela Unit Consumed tih kha en kha, Consumer details box a a hnuai bera Contracted load tih kha en bawk la, khami pahnih atang khan i bill chawi zat tur awlsam takin i chhut ve thei dawn tihna a ni.
Entirna:
1. Contracted load kha 0.3 kw ni ta se, unit consumed kha 27 ni ta se, I bill chawi zat tur chhut dan chu hetiang hi a ni ang – Contracted load 0.3 leh fixed charge Rs 50 i puntir ang a, i unit chawi zat 27 leh unit 1 hman man Rs 4.80 i puntir bawk ang. Chumi chhuak pahnih chu i bill chawi zat tur chu tihna a ni. (0.3x50 =15, 27x4.80=129.60, 15+129.60=144.6 hei hi I bill chawi zat tur a ni.
2. Contracted load ah 2 nita se, Unit consumed ah 169 ni ta se hei hi kan bill chawi zat tur a ni ang-
Fixed charge 2 kw x Rs 50 = Rs 100
Unit consumed 169
a) 100 x 4.80 = Rs 480
b) 69 x 5.50 = Rs 379.50
TOTAL (100+480+379.50= Rs 959.50 hi kan bill chawi tur a ni ang.)
Tiang hian awlsam takin kan bill chawi hi a dik em, kan eng chhit ral leh kan bill chawi hi a inmil em? Tih te awlsam takin mipui ten kan chhut ve thei a ni. Diklo a awm anih chuan Department hotute hnenah arang lama complaint thin tur a ni.
Source :
1) Article of H.Laldikliana, MCU Aizawl.
2) P & ED Traiff Order for FY 2021-22.
A bengvâr thlâk e
ReplyDeleteAva á¹ha em, ka dah á¹ha hmak e
ReplyDeleteContracted Load chungchangah hian Contracted Load hniam lutuk hi siamrem theihna dan a awm a, P&ED Tarif Order 1.10. in a tralan dan chuan Contracted load 0.5 kW aia hniam chu 0.5 kW anga siamrem/siampum theih a ni a. 0.5kW chin chunglam erawh chu a nihna ang anga chhut tur a ni thung.
ReplyDelete1.10. Rounding of Contracted Load/billing demand: For the purpose of calculation of fixed/demand charge in the monthly billing, the contracted load/billing demand shall be taken on actual basis as recorded by DISCOM office. In case, if the contracted load/billing demand found lesser than 0.5 kW or kVA shall be rounded up as 0.5 kW/kVA as the case may be. While all contracted load/billing demand above 0.5 kW/kVA shall be taken as per actual details recorded in the consumer historical
profile data maintained by the Licensee. The Licensee should update Contracted load/Billing demand as per the provisions of clause-4.108 of JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013 (with up to date amendment).